Downtime non pris en compte lorsque déjà passé ?

  • May 18, 2022
  • 2 replies
  • 224 views

Maxime-koe
Forum|alt.badge.img+3

Bonjour,

[FR]

est-ce que c’est normal de ne pas pouvoir créer de downtime sur un hôte ou service dans le passé ?

car cela fausse mon rapport de disponibilité d’infrastructure qui a le modèle “BV-BA-Availabilities-1”.

[EN]

is it normal not to be able to create downtime on a host or service in the past?

because it skews my infrastructure availability report which has the pattern "BV-BA-Availabilities-1".

 

Bonne journée / good day

Best answer by sduret

Hello @Maxime-koe 


Yes it’s normal, you can’t add a downtime in the past.

Even if you set a start date in the past, the downtime will really start when Centreon Engine will receive the command.

In addition of that, events and availabilities are calculated every night.

Regards

2 replies

sduret
Centreonian
Forum|alt.badge.img+13
  • Centreonian
  • Answer
  • May 18, 2022

Hello @Maxime-koe 


Yes it’s normal, you can’t add a downtime in the past.

Even if you set a start date in the past, the downtime will really start when Centreon Engine will receive the command.

In addition of that, events and availabilities are calculated every night.

Regards


Maxime-koe
Forum|alt.badge.img+3
  • Author
  • Steward **
  • May 20, 2022

Hello,

 

thank for that answer, i thought it was doable!

 

 

BR,

good day!